In the context of a general renewal of the Universitätsspital Zürich, the NORD2 ward on floors E and F was renovated. The inpatient ward, originally built in 1992, no longer met current standards.

On an area of approx. 5000m2, four wards with 140 beds as well as treatment rooms were built. The renovation was carried out in phases during ongoing operation. The last stage was completed in spring 2021.

Client

Universitätsspital Zürich

Architect

Itten+Brechbühl AG

Location

Zurich

Use

Hospital ward

Key Dates

2018-2021 | Planning and realisation
2021 | Commissioning

Our Role

Client consulting

Our Tasks

Cost-, scheduling- and quality-assurance, PQM

Photos/Visualisations